Improved pedestrian safety
More logical vehicle and foot traffic flow
Enhanced campus connectivity and integration
Increased number of parking spots
Expansion of the Main Parking Lot, adding 80+ parking spaces
Relocation of Westhampton Drive to accommodate Main Lot expansion
Addition of:
o New pedestrian walkways (including alongside Caddie Hill Road)
o A 4-way stop at the intersection of Caddie Hill Road/Westhampton Drive
o A drop-off zone adjacent to the Upper Terrace
o Additional safety and traffic calming measures
Right-sized infrastructure (stormwater, lighting, security cameras)
Amplified pressure on parking for members and staff
Alternate pedestrian routes in each project stage
Fencing around construction areas and directional signage for pedestrian and vehicular traffic
Single-lane traffic on Caddie Hill Road as needed during work (flagger will direct traffic, one lane will always remain open)
Temporary closures of Westhampton Drive at specific, scheduled times (will be communicated ahead of time)
Golf Course Architect Andrew Green consulted on construction and golf impact
November 10, 2025 through Spring 2026
The project is intentionally phased to preserve reasonable walking paths, keep Caddie Hill Road open, maintain at least one main entrance at all times, and retain a portion of parking in the Main Lot at all times.