Main Dining Room
Scaffolding has been erected as high-ceiling work progress continues, including the installation of acoustic panels and lighting set-up
Epoxy floor application has begun
Private Dining Room
Drywall installation is complete and the initial stages of priming and painting have begun.
Kitchen
Drywall installation is well underway and the initial stages of priming and painting have begun.
Two walk-in coolers have been installed.
Duct work installation is underway.